Saturday 11th July 2026
Another day in the oven!! At least it was cool first thing and the good thing about the Vulcan is the shade it provides under the wing. With a slight breeze its really cooling under the wing. We hate that effect in winter but at this time of year it’s more than welcome.
Those volunteers that came today were mostly on site shortly after 8am. I think we all had the same idea and needless to say the painters were set up early and up on the port wing. They paid the price later and took the opportunity for an early finish. I can’t say I blame them.
The facilities guys were also on the case early…they always are. They soon retreated to their favourite place which seems to be the roof of our containers. They are more resourceful and set up a gazebo up there to protect themselves from the sun. They also had some repairs to do on the electrics as a cable had been accidentally trapped in the locking mechanism of one of our containers recently. It didn’t take long for them to fix it. Their other task which is progressing nicely is our tea bar. My concern is that its looking so good we won’t get anyone on the pan in the winter!
So that takes us to the main task on the aircraft today. We have a few things to do but with the weather forecast to heat up we held back on a few things and focussed on the re installation of our AAPP. With the unit installed in the wing last Saturday it was about connecting all the cables, fuel lines and ensuring anything requiring wire locking was addressed. The team re assembling was not the one that disconnected it a few weeks back so there was plenty of room for a bit of consultancy. However, by around 4pm we were ready to attempt a start, We knew it would take a few attempts as the unit had been drained of fuel. It would take a few attempts to prime the system. Needless to say it did fire up after a few attempts and the good news is that the EGT gauge worked perfectly which was the reason for removal in the first place. The bad news is that the AAPP is there to provide a source of electrical power and that didn’t go quite so well. Actually it didn’t go at all as we had no output. It took bit of head scratching and a spell of looking at the manuals before retracing our steps. The way this aircraft is designed it took a bit of climbing to check terminals located above and behind the stbd undercarriage. Then we spotted our mistake which was a crossed connection. It was quickly resolved and another start proved the alternator was working fine. It was great to see that EGT gauge working once more too. Next week we’ll start on another maintenance task as we intend to replace all the terminals of our alternators. That’ll keep us occupied!
The winch refurb: Our volunteer managed to remove one of the actuators after a bit of a struggle this morning. Although it still took some heat and a bit of percussion I sense it wasn’t the usual battle so at least he never spent the whole day laying on the pan. I think this battle is being more easily won now but it’s taken a lot of effort.
We have an away team at Woodford this weekend at their Wings & Wheels event – They report a good time was had by all on day one, the new merch lines were popular, and lots of people were interested in our work and the partnership we have with the XM603 team at
Avro Heritage Museum
Finally I can’t go without thanking our visitors for coming today . There were plenty of you for sure and we thank you for your donations, we couldn’t do it without you.
Saturday 4th July 2026
Another dry and sunny day at Wellesbourne. Although it was overcast first thing it didn’t take long to warm up. The painters arrived early to continue with the port wing but as the wind was blowing I think they remained cool despite the early sunshine.
The building maintenance team were also on site early progressing the build of our new crew room whilst other members of their team took to the roof of our containers applying rust remover to the bad areas. They are talking about replacing one containers roof so they’ll be some welding practice soon for sure but the repair should work out cheaper than replacing the container. I also believe the materials will arrive next week allowing them to put the roof over the outdoor grinding bench.
Work also continued on the Sentinel winch which is looking very nice these days. That tug must have looked great when it was first delivered to the RAF and you get a feel for its appearance now that the refurb is progressing. Most of today’s winch painting took place on the underside of the assy. But I think the heat and hammering has done the trick with all the parts that should move now able to do so with ease. The weather is definitely helping on this task too, particularly as our volunteer has to spend most of his time laying on the pan under the tug.
Work on the aircraft was largely focussed on the refit of AAPP. The team had completed the replacement of the thermocouples last week so we now need to place the unit back into the stbd. Wing. Before we could do that we needed to upgrade our mini hoist. When the team had lowered the AAPP a few weeks back the winch operator was precariously balanced on a chair as the pole between the winch hook and the winding mechanism was a bit short. The team acquired a new longer pole which was then modified to fit. Unfortunately the pole was just a few thou. larger in diameter than the old pole so before we could assemble the winch we had to resort to the use of a file and emery cloth to get the pole to fit. It seemed to take an age but by the end of the morning we were in a position to set the winch up in the AAPP bay and get ready to hoist it into place. Of course nothing is straightforward and it was noticed that the anti vibration mounts of a pressure sensor were perished. There is no way these could be replaced once the AAPP is back in place so a hasty design meeting was called followed by a hunt for suitable parts. A replacement vib. mount was assembled during the lunch hour and fitted straight after lunch. Great teamwork and the lift took place soon afterwards.
Needless to say our frustration never really goes away and the gremlins decided to focus on the AAPP mounting points. There are 3 of them and you have to raise the AAPP to the roof of the bay an then line up 2 bolts and a pip pin to secure the AAPP before detaching and removing the winch. The good news the winch operator was no longer sat precariously whilst winching, the bad news was that having hauled up the winch it took an age to align the AAPP attachment points. Needless to say the team won in the end but it took a number of breaks and a variety of tools and initiatives before we got there.
You might think that having finally got the AAPP fixed in the aircraft this might be a good time to stop but our volunteers are quite inquisitive and someone had mentioned that the cartridge start attachments were possibly stuck and possibly corroded in their mounts. Well they couldn’t resist checking the 2 cartridge assemblies out. They were stuck but with a bit of gentle persuasion they were removed and the 2 fired cartridges were successfully removed. Its been mildly frustrating day but the AAPP is fitted, the winch has worked and the old start cartridges have been taken out. Next Saturday will see the fuel pipes and electrical connections refitted and then we’ll fire up the AAPP to check out then original fault which was the failure of the EGT gauge.
So that ends another full day at the Vulcan. No pre arranged visits today but plenty of drop ins so our visits team were kept fully occupied. Thanks to our visitors for coming, its always good to see you.
Now it’s time to look forward to next Saturday, where we have an away team taking a stall up to the Avro Heritage Museum for the weekend, joining in with their Wings and Wheels event! (If they manage to fit all the goodies into the car!)
More sunshine for us and them, I hope.
Saturday 27th June 2026
Thankfully it was a bit cooler today but not by much.
It was refreshing to be under the wing with a nice breeze to keep you cool, but venture into the storage containers and it was a different story! However, there was a lot going on despite the heat and today’s summary will definitely end on a positive note.
There were no booked visits and I don’t think the Houchin was fired up all day, However we had plenty of ‘drop ins’ and our visits team seemed fully occupied. I bet the cockpit was hot though despite our best efforts with an aircon unit fitted below the P1/P2 floor.
Our early starters were on site around 7am largely to get ahead of the heat build up on the pan. The team included the painters. They made an early start last week but got caught out by the rain. There was definitely no rain today and with a delivery of fresh paint they could have made good progress.
Those of you who are members may well have seen the latest issue of our newsletter. If so you might have seen the pic with the crow on the cockpit roof. Some of our volunteers weren’t happy with the state of the paintwork so they set up some steps to access the windscreen area only to find corrosion on the wiper arms and deterioration of the wiper blades. That occupied a bunch of people removing the arms then removing the corrosion before filling the affected areas. The arms seem re-usable but there’ll be some searching for replacement blades next week.
The next job was to be the wirelocking of the couplings disturbed during the recent refuel valve refurb. If you remember the stbd wing was pretty much completed last Saturday but our willing volunteer wasn’t with us today so the task was passed to a new team. I’m pleased to report that the job was finished today so that’s definitely a big win.
It won’t surprise anyone to learn that there was more heat and hammering be applied to the tug winch. It seems that some parts were victims of water ingress over many years so needless to say they are virtually welded together. Unfortunately everything needs to move freely so there’s been a massive amount of heat applied to the corroded components. I’m sure something will give soon but its been a full day of hammering and banging. Something’s got to give soon!
The AAPP has received a lot of attention today with the installation of the new thermocouples following the manufacture of thread adaptors. The thermocouples were all installed then the cables were fed through a conduit before being cut to length, stripped and installed into a terminal block on the front firewall. Each thermo couple was then heated up with a blowtorch with the outputs successfully tested on a meter. Its all looking good so we may be on for an AAPP install next weekend.
Talking of the AAPP installation, some of our volunteers have been modifying the winch used to remove the AAPP a few weeks back. I hadn’t realised that the winch poles were a bit on the short side. This made it difficult for the winch operator to find a comfortable position to work. They’ve made a new longer pole this week which was no mean feat. It never ceases to amaze me when it comes to the ingenuity of our volunteers and I can’t wait to see the winch in action,
One other piece of ingenuity today concerned a sealed component in our refuelling power supply. It has a sealed vibrator which I guess would have been swapped ‘in the day’. We don’t have that luxury any more so the vibrator was cut open with a Dremmel exposing the corroded contacts. These were thoroughly cleaned and after a few frustrating attempts the vibrator worked once more. I think we were all surprised but this has generated an extra ‘spare’. Great stuff !!
So another successful and satisfying day at Wellesbourne. I hope all our visitors left happy, we did!
Back for more next Saturday. Can’t wait.
Saturday 20th June 2026
One pre booked visit today – Today’s group was Douglas motorcycles who brought some very nice machines with them, some of which I guess could be called ‘vintage.’ They looked in great condition!
Their 13.30 arrival gave us plenty of time to work on site which, as usual, started long before I arrived at around 8am. The usual suspects were busy on site and getting stuck into our facilities modifications. They had set up a couple of gazebos in expectation of working on the roof parts of our external bench but they were thwarted by a lack of stores which would have enabled them to felt the roof today. Undaunted they then set to on the roof of our No3 container which is a bit rusty and has holes in it. They had mixed fortunes up there as we had a spell of unexpected rain first thing. Luckily there’s plenty for them to do and the next time I looked they were working on our ‘tea bar.’ At least it was drier than their other options. Despite the changeable weather I think they managed to apply rust inhibitor to the roof of our container before the end of the day but the roof of the outside bench will have to wait a while longer.
On the aircraft, one of our painters came in early to make an early start on the port wing. Unfortunately he was also a victim of the early rain showers. At least the weather improved as the day progressed and by COP he was asking me if I would acquire some more paint for next weekend. He did look warm as the day heated up!
Other volunteers were completing jobs that had largely been wrapped up last weekend. The refuel valves have all been refurbished but the larger fuel coupling nuts need to be wire locked. With 14 tanks that’s a lot of wire locking but our willing volunteer managed to complete both of our No2 tanks, No4 tanks and Nos 3,5,& 6 tanks on the stbd side. That sounds like a good day’s work to me.
Another team was completing the installation of our replacement fire bottles in the port wing. Needless to say this also involved wire locking with next to no access to the fasteners where they are installed. They were on this job for most of the day and it was finished around 5pm so fair play for their perseverance. The other job in support of the fire extinguishers replacement was the refit of a wing panel which had been removed for inspection purposes after the fire bottles were accidentally discharged. Unfortunately this is a panel which is held in place by at least 100 rivets. The panel was cleaned, painted and re re riveted before we left. Another great job.
It goes without saying that the winch job on our tug was going on in the background. Re assembly is definitely well under way and the parts are looking as though they are aligned now. There are some new bolts to be acquired and the ground anchor is yet to be re attached but its great to see bearings and other component parts looking like new. Its definitely a job that was well overdue but the volunteer involved is clearly doing it justice.
Work continued on the AAPP EGT fault and new thermocouples have been sourced. The guys are working on adaptors to fit the new metric thermocouple fittings into an aircraft which was manufactured in imperial measurements. I’m confident the team will have a solution shortly and the AAPP will be refitted v.soon.
We received some lovely new merch in the shop too – see if you can spot the subtly placed shiny new water bottles in the pics(!) We’re hoping to get them on the webstore this week or you can get one at Wellesbourne next Saturday for just £10 – bargain!
So that just leaves me to thank our visitors for coming to see us today. We had loads of ‘drop in’ visitors as well as our pre arranged group. I hope the guides’ enthusiasm was felt by you all and you enjoyed your time with us. We’ll be back next Saturday for more fun, feel free to pop along. We’d love to see you.
Saturday 13th June 2026
After a wet and blustery week we had a glorious day at Wellesbourne today, with cloud clearing by mid-morning to reveal warm sunshine which lasted for the rest of the day.
Today was what we call an Engineering Day with no booked visits so the engineering crew had unrestricted access to the aircraft. The main task was to remove the AAPP so that we could investigate the failure to indicate jet pipe temperature. Over the last few weeks we have checked everything we could access with the unit in the airframe and haven’t found the fault, so the only remaining option was removal. Much of the disconnecting was done last week, so it only took a couple of hours to lower the unit into our makeshift stand.
Once the covers were removed for access, a very quick test revealed that all four thermocouples had failed. The way the circuit is configured, it is quite possible that three have been defective for some time, and it only became apparent when the last one failed. With considerable use of a blow torch to persuade the nuts to loosen, and some swearing at inaccessible cable clips, we were able to remove the complete thermocouple harness. The task now will be to find suitable replacement thermocouples to allow us to make up a replacement harness.
The final refuelling valve, which had been refurbished last week, was reinstalled in no.4 port tank, and at the end of the afternoon we moved 500 lbs of fuel into the tank and confirmed we had no leaks. That has been an ongoing project for some time and at long last we have all fourteen valves finished, so hopefully we will no longer have fuel migrating from tank to tank.
More progress was also made on the Sentinel winch overhaul with cleaning and painting of some of the winch cable guides and attention to the bearings.
No work today on our kitchen cum crew room which is waiting for materials, but we were able to get the timber sheeting cut for the roof over our outdoor welding and grinding area, so as soon as the water proofing material arrives that can be installed and completed.
Despite no booked visits we still had a steady stream of drop-in visitors, so our guide was kept busy all day. We hope everyone who came enjoyed their visit. We certainly had a great day and we’ll be back to do it all again next Saturday. Maybe you’ll come along and say hello.
Saturday 6th June 2026